Ofankor, Tema, Klagon, Spintex, Trasacco, Dzorwulu, and Achimota are to undergo a 6-day load-shedding programme according to a statement by the Electricity Company of Ghana (ECG) starting today.
In a statement released by the power distribution company, the power outages will last till Thursday, May 14.
The load-shedding is to enable ECG to convey some transformers from the Tema Port to its Pokuase Bulk Supply Point (BSP) construction site.
“The Electricity Company of Ghana (ECG) Limited wishes to inform the general public, especially our cherished customers in the under-listed areas that, to ensure safe conveyance of 145MVA transformers from the Tema Ports to the Pokuase Bulk Supply Point (BSP) construction site, the company will have to isolate some High Voltage overhead lines,” ECG said.
“In this regard, there will be planned outages from Friday 8th May 2020 to Thursday, 14th May 2020 between 10:00 pm and 1:00 am each day.”